How Long Does a Bathroom Renovation Take? Step by Step

The question we hear most is how long the job will take. The honest answer is that it depends on the room, but the order of work is almost always the same. Knowing the steps helps you plan for the days without a bathroom and see why some stages cannot be rushed. These timings are a guide only, and we confirm the real ones for your home in writing.

Tiles, a vanity unit and boxed bathroom fittings stacked in a spare room ready for fitting
Call now

Before the work starts

The renovation starts weeks before a fitter arrives. First we visit, look at the room and talk about what you want. Then we agree a design, a list of fittings and a quote. You choose tiles, the suite and any extras, and we order them.

Ordering is the stage that most often sets the start date. A suite and tiles can be in stock or can take some weeks to arrive, especially for made-to-order furniture or unusual tile sizes. We prefer to have everything delivered and checked before we start, so the job is not held up in the middle.

Bathroom wall boarded and waterproofed with new pipework ready for tiling

Step 1: Taking out the old bathroom

The first day is usually the strip-out. We protect the floors and the route through your home, then take out the bath, basin, toilet and any old tiling or boards. We isolate the water and cap the pipes so that the rest of the home keeps running.

This is the noisiest and dustiest day. It is also when we see what is behind the walls, which is why we ask you to be reachable on this day in case we find something that needs a decision.

Step 2: Pipes, electrics and the floor

Next comes the first fix. This means the new pipework, waste pipes and any electrical cable for lights, a fan or a heated mirror. We deal with the floor at this stage too: levelling, replacing weak boards, or forming a base for a shower tray.

Any new drain or change to the layout happens here, and it is the stage most affected by what we find. An old pipe that needs replacing adds time. A straightforward like-for-like layout moves quickly.

Step 3: Walls, boarding and waterproofing

Once the pipes are in, we board and prepare the walls. Where you will have tiles, the walls need to be flat, dry and firm. In a shower area we waterproof the boards and the corners so water cannot get behind the tiles.

Some materials need time to dry or cure before the next step. Plaster, levelling compounds and waterproofing products each have their own drying times, and we follow the maker's instructions rather than hurry them. This is one reason a bathroom is not a one-day job.

Finished bathroom with a new white suite, grey tiles and a glass shower screen

Step 4: Tiling and grouting

Tiling is often the longest single stage. Floor and wall tiles go on, and then the adhesive needs time to set before grout goes in. A room tiled floor to ceiling takes longer than one with partial tiling, and large or patterned tiles need more careful cutting and setting out.

Grout then needs to dry before we can seal it and use the shower. We tell you when the shower is ready for use, because using it too early can spoil the finish.

Step 5: Fitting the suite and finishing

With the tiling done, the second fix begins. We fit the bath or shower tray, the screen, the toilet, basin and vanity, the taps and shower valve, the towel rail and the accessories. The electrician returns to connect the lights and fan.

Then we seal the joints, paint what needs painting, fit the flooring edge trims, and clean the room. We test the water, check for leaks and look at every joint with you. Anything we want to adjust is put right before we leave.

Typical timings and what changes them

For a standard-size bathroom with the layout kept the same, most renovations take around one to two weeks on site. A bigger room, a new layout, a walk-in shower with a formed floor, or a lot of tiling can take longer. Hidden problems found when the old room is out can add days.

As a rough guide, these things lengthen the job:

  • Moving the toilet, bath or shower to a new position.
  • A floor that needs levelling or new boards.
  • Replastering walls before tiling.
  • Large or patterned tiles, or tiling to the ceiling.
  • Waiting for delivery of a missing part.
  • Access problems such as a high flat with a narrow stair.

Living at home without a bathroom

Many families stay at home during the work. It helps to plan for the days without a bathroom. If you have a second toilet or shower, tell us and we will keep it clear. If not, think about family, friends or a gym for showers on some days.

We try to keep the water off for as short a time as we can, and we tell you in advance when it will be off. We cover the floors and clean up at the end of each day so the rest of your home stays livable.

Planning your dates

Avoid fixing a hard deadline, such as a family visit or a wedding, to the first day of the work. Leave a few days of space at the end. If something does go wrong, that space protects your plans.

If you would like to know what shapes a quote as well as a timetable, read what affects the price of a bathroom renovation in Scotland. If you live in a flat, renovating a tenement bathroom covers the extra planning.

Your next step

Tell us when you would like the work done and we will say what is realistic. Call now to talk about your timetable, or see how our bathroom renovations work.

Common questions

Call now

How many days will I be without a bathroom?

It depends on the job. We tell you in advance which days the water will be off, and where possible we keep the rest of your home running.

Why can't the shower be used straight away?

Adhesive, grout and sealant need time to set. Using the shower too early can spoil the finish and let water behind the tiles.

Can the job run over the agreed time?

It can if hidden problems turn up or a delivery is late. We tell you as soon as we know and explain the effect on the dates.

Do I need to be at home?

Not all the time, but we ask that someone is reachable on the first days, when we see what is behind the walls.

Get a firm price for your bathroom

Tell us about your bathroom and we will arrange a free home design appointment. Call now or send a few details and we will come back to you.

0141 489 0664
  • Home showroom appointments
  • Finance from £24 a week*
  • Modern bathroom styles
Call now

Your details are used to answer your bathroom enquiry. See our Privacy Notice for the full picture.

Call now